Will a new oversight position help California's high-speed rail plans get on track?

A new state-level position will oversee development of California's high-speed rail, which has been plagued with cost overruns. Courtesy California High-Speed Rail Authority.

After a decade of cost, schedule, technical, regulatory, personnel and legal problems, the California high speed rail project will be getting an inspector general soon as part of a deal between Gov. Gavin Newsom and the Legislature.

The new investigative position is intended to intensify oversight and improve performance of the $105 billion railroad project. Enthusiasm for the change is high, but whether it will fix everything is uncertain, even among state leaders.

"There is nothing but problems on the project," said Speaker Anthony Rendon, a Lakewood Democrat. "The inspector general provides oversight and some sense of what is going on with management. That has been missing for a long time."

But will it work?

"We don't know," Rendon said. "We need to be vigilant. The IG will provide what we need to carry that out."

Help sustain the local news you depend on.

Your contribution matters. Become a member today.

Join

Until now, a variety of outside agencies have advised the Legislature and the governor on the project, resulting in recommendations that often were not carried out. In some cases, they required changes that nobody had the power to make and in other cases carried too high a political price with outside interest groups.

In 2012, the Legislative Analyst's Office recommended against an appropriation to start construction, arguing the California High-Speed Rail Authority wasn't prepared. Gov. Jerry Brown lobbied the Legislature for it and won. Now, many agree the LAO was right. The Peer Review Group has long warned that the state needs a secure financing plan. But the project proceeds without one.

Such outside advisors have lacked the resources and the mission to intensively delve into the day to day work of the rail project, its army of consultants and its stable of international contractors.

"The IG will bring a level of oversight that we have not had before," said Helen Kerstein, the lone bullet train expert at the Legislative Analyst's office. "This is very powerful."

The law creating the inspector general lists a wide range of authorities the new office will have: full access to all the project's records; authority to review contracts and change orders; and issuing subpoenas for witnesses and records, among much else.

Stay informed

Get daily headlines sent straight to your inbox in our Express newsletter.

Stay informed

Get daily headlines sent straight to your inbox in our Express newsletter.

"It is not some person sitting in a basement," said Laura Friedman, chair of the Assembly Transportation Committee who is widely credited with pushing through the inspector general idea. "It is going to be staffed. It is going to be real."

That would include investigating waste, fraud and abuse, as well as working with law enforcement and prosecutors, she said.

What the position might look like

How big an organization will it require? So far, there is no budget. But the inspector general for the high-speed rail project would be paid the same as the inspector general for the California Department of Corrections and Rehabilitation, who makes $192,382 and will have a staff of 212 in the coming fiscal year.

Fred Weiderhold, a West Point civil engineer who served for 20 years as Amtrak's inspector general, said if he were taking the California job, he would want to start with a staff of at least 50 people, half auditors, 30% investigators and 20% inspectors and evaluators.

"It is a daunting job," Weiderhold said about the California project. "You have to follow the money. I guarantee you that on any project this large you will have fraud, product substitution and waste."

By the time Weiderhold left as Amtrak inspector general, he had helped put several hundred people in jail and caused 2,000 people to be fired.

The high speed rail inspector general will not have authority to control actual spending, a decision that was considered and rejected by Newsom.

A more aggressive plan was followed by the Massachusetts Bay Transportation Authority in 2015, when it faced a breakdown in Boston area service and spiraling capital cost overruns. State lawmakers fired the authority's existing board and installed a new Fiscal and Management Control Board.

Estimated construction costs on a 4.3 mile extension of a light rail line had grown from $1 billion to $2 billion, said Joe Aiello, the board's chair. The board stopped work, threw out existing contractors and put in an independent team to evaluate what was going wrong, he said.

"There was outrageous scope creep," Aiello said.

By the time the board was dissolved last year, the construction cost had been hammered back down to $1 billion, he said.

State still needs actual train

Even while increasing oversight, the deal doubles down on the bullet train mission. An appropriation will release $4.2 billion from a 2008 bond fund, but only for completing a 171-mile Central Valley segment from Bakersfield to Merced.

"They need to deliver something soon that the public understands is a train," Friedman said.

Newsom met another Assembly demand by adding $3.5 billion for transit projects in the Bay Area and Southern California, as well as $300 million to fix an Orange County Amtrak rail that is ready to fall into the Pacific.

"You can't have enough oversight on a project like this," Friedman said. "This is not a minor change. It will be a very big change for the project."

Craving a new voice in Peninsula dining?

Sign up for the Peninsula Foodist newsletter.

Sign up now

Email Ralph Vartabedian at [email protected]

CalMatters.org is a nonprofit, nonpartisan media venture explaining California's policies and politics. Read more state news from CalMatters here.

Follow Mountain View Voice Online on Twitter @mvvoice, Facebook and on Instagram @mvvoice for breaking news, local events, photos, videos and more.

Will a new oversight position help California's high-speed rail plans get on track?

by Ralph Vartabedian / CalMatters

Uploaded: Tue, Jul 19, 2022, 9:26 am

After a decade of cost, schedule, technical, regulatory, personnel and legal problems, the California high speed rail project will be getting an inspector general soon as part of a deal between Gov. Gavin Newsom and the Legislature.

The new investigative position is intended to intensify oversight and improve performance of the $105 billion railroad project. Enthusiasm for the change is high, but whether it will fix everything is uncertain, even among state leaders.

"There is nothing but problems on the project," said Speaker Anthony Rendon, a Lakewood Democrat. "The inspector general provides oversight and some sense of what is going on with management. That has been missing for a long time."

But will it work?

"We don't know," Rendon said. "We need to be vigilant. The IG will provide what we need to carry that out."

Until now, a variety of outside agencies have advised the Legislature and the governor on the project, resulting in recommendations that often were not carried out. In some cases, they required changes that nobody had the power to make and in other cases carried too high a political price with outside interest groups.

In 2012, the Legislative Analyst's Office recommended against an appropriation to start construction, arguing the California High-Speed Rail Authority wasn't prepared. Gov. Jerry Brown lobbied the Legislature for it and won. Now, many agree the LAO was right. The Peer Review Group has long warned that the state needs a secure financing plan. But the project proceeds without one.

Such outside advisors have lacked the resources and the mission to intensively delve into the day to day work of the rail project, its army of consultants and its stable of international contractors.

"The IG will bring a level of oversight that we have not had before," said Helen Kerstein, the lone bullet train expert at the Legislative Analyst's office. "This is very powerful."

The law creating the inspector general lists a wide range of authorities the new office will have: full access to all the project's records; authority to review contracts and change orders; and issuing subpoenas for witnesses and records, among much else.

"It is not some person sitting in a basement," said Laura Friedman, chair of the Assembly Transportation Committee who is widely credited with pushing through the inspector general idea. "It is going to be staffed. It is going to be real."

That would include investigating waste, fraud and abuse, as well as working with law enforcement and prosecutors, she said.

What the position might look like

How big an organization will it require? So far, there is no budget. But the inspector general for the high-speed rail project would be paid the same as the inspector general for the California Department of Corrections and Rehabilitation, who makes $192,382 and will have a staff of 212 in the coming fiscal year.

Fred Weiderhold, a West Point civil engineer who served for 20 years as Amtrak's inspector general, said if he were taking the California job, he would want to start with a staff of at least 50 people, half auditors, 30% investigators and 20% inspectors and evaluators.

"It is a daunting job," Weiderhold said about the California project. "You have to follow the money. I guarantee you that on any project this large you will have fraud, product substitution and waste."

By the time Weiderhold left as Amtrak inspector general, he had helped put several hundred people in jail and caused 2,000 people to be fired.

The high speed rail inspector general will not have authority to control actual spending, a decision that was considered and rejected by Newsom.

A more aggressive plan was followed by the Massachusetts Bay Transportation Authority in 2015, when it faced a breakdown in Boston area service and spiraling capital cost overruns. State lawmakers fired the authority's existing board and installed a new Fiscal and Management Control Board.

Estimated construction costs on a 4.3 mile extension of a light rail line had grown from $1 billion to $2 billion, said Joe Aiello, the board's chair. The board stopped work, threw out existing contractors and put in an independent team to evaluate what was going wrong, he said.

"There was outrageous scope creep," Aiello said.

By the time the board was dissolved last year, the construction cost had been hammered back down to $1 billion, he said.

State still needs actual train

Even while increasing oversight, the deal doubles down on the bullet train mission. An appropriation will release $4.2 billion from a 2008 bond fund, but only for completing a 171-mile Central Valley segment from Bakersfield to Merced.

"They need to deliver something soon that the public understands is a train," Friedman said.

Newsom met another Assembly demand by adding $3.5 billion for transit projects in the Bay Area and Southern California, as well as $300 million to fix an Orange County Amtrak rail that is ready to fall into the Pacific.

"You can't have enough oversight on a project like this," Friedman said. "This is not a minor change. It will be a very big change for the project."

Email Ralph Vartabedian at [email protected]

CALmatters.org is a nonprofit, nonpartisan media venture explaining California's policies and politics.

Comments

Dan Waylonis
Registered user
Jackson Park
on Jul 19, 2022 at 11:01 pm
Dan Waylonis, Jackson Park
Registered user
on Jul 19, 2022 at 11:01 pm

The ongoing debacle of this HSR indicates that our CA politicians are not grounded in reality. Just a tiny bit of analysis would shut it down immediately. Instead, state and federal funds are being squandered.


ivg
Registered user
Another Mountain View Neighborhood
on Jul 20, 2022 at 6:31 am
ivg, Another Mountain View Neighborhood
Registered user
on Jul 20, 2022 at 6:31 am

It's instructive to compare this situation with the adjacent headline: "Four arrested for allegedly stealing $50K worth of lululemon merchandise"


Seth Neumann
Registered user
Waverly Park
on Jul 20, 2022 at 12:14 pm
Seth Neumann, Waverly Park
Registered user
on Jul 20, 2022 at 12:14 pm

The only way to make this turkey fly is to broker some sort of deal with major Silicon Valley employers to fund the San Jose to Modesto (or is it Merced? Have mercy!) section and use it to colonize the Central Valley as Silicon Valley bedrooms. We can export our overcrowding and reduce pressure on water and schools here and provide a feeder to the north end of the high speed rail to no where. The Southern end is a civil engineering nightmare (look into the history of the Old Southern Pacific's attempts to build a direct route from Bakersfield to LA -- rather than Tehachapi and Cajon passes) and will probably never be built.


Don't miss out on the discussion!
Sign up to be notified of new comments on this topic.

Post a comment

In order to encourage respectful and thoughtful discussion, commenting on stories is available to those who are registered users. If you are already a registered user and the commenting form is not below, you need to log in. If you are not registered, you can do so here.

Please make sure your comments are truthful, on-topic and do not disrespect another poster. Don't be snarky or belittling. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

See our announcement about requiring registration for commenting.